CONSTRUCTION BLOG: DICK + JANE
Archives
COMPLETEBoth Homes in Contract!
OPEN HOUSE MARCH 13 FROM 1-4PM // Posted on
Interior Stair
Stucco
Countertops
Interior Stair
Stucco Siding
Drywall, Siding, Tile
Drywall
Wrapped
Framing and Roofing Complete
Facade Framing
Framing Nearing Completion
Framing Has Begun
Slabs Poured
Underground Plumbing
Eastsider LA Interview
Waterproofing and Tomatoes
Second Garage Poured
First Garage Poured
Formwork
Footings Poured
Dick + Jane are Underway
Excavation Continues
Excavation
Groundbreaking!
Land Acquired
Subscribe
→Stucco Siding
by
Kevin 12/13/10
The cement board siding is completely installed and the stucco brown coat is on. On the interiors the only items left are the countertops, flooring, and finish plumbing. It looks like the homes will be ready for sales in early 2011 as planned!