Inside: DICK + JANE
$679,000 Each
1124 + 1126 Echo Park Avenue, Los Angeles, CA 90026 / Two Single Family Homes / 1610 sq. ft. each
These homes are located steps from Echo Park lake near downtown LA. Each home is 3 bed, 2 bath.
CONSTRUCTION BLOG: DICK + JANE
Archives
COMPLETEBoth Homes in Contract!
OPEN HOUSE MARCH 13 FROM 1-4PM // Posted on
Interior Stair
Stucco
Countertops
Interior Stair
Stucco Siding
Drywall, Siding, Tile
Drywall
Wrapped
Framing and Roofing Complete
Facade Framing
Framing Nearing Completion
Framing Has Begun
Slabs Poured
Underground Plumbing
Eastsider LA Interview
Waterproofing and Tomatoes
Second Garage Poured
First Garage Poured
Formwork
Footings Poured
Dick + Jane are Underway
Excavation Continues
Excavation
Groundbreaking!
Land Acquired
Subscribe
→Facade Framing
byKevin 09/21/10
The final shape of the buildings is coming together.
→Framing Nearing Completion
byKevin 09/15/10
Framing is about 90% complete as of today. The mechanical, electrical, and plumbing are also roughed in. We hope to start on the insulation sometime next week.
→Framing Has Begun
byKevin 08/09/10
Now that the slabs are in the spaces are starting to take shape. We hope to have the majority of the framing complete by the end of the month.

That poor little baby banana plant in the foreground is about to get transplanted to our office garden.
→Slabs Poured
byKevin 08/04/10
We are finally out of the ground! The slabs were poured today and the project finally looks like something.
Here they are placing the last couple of yards of concrete. The pour took 45 yards for both houses which is 5 trucks of concrete. Warren (the guy holding the hose) is the pump operator. We've been working with him for about 8 years on all our hillside projects. He pumps the concrete from the truck to the slab and then the concrete sub finishes it. The slab shown has two layers of massive #8 rebar (the steel that works in tension with the compressive strength of the concrete) which is 1" thick.
The obvious things to look out for are: #1: Is all your structural hardware in the right location #2 Is all your rough plumbing in the right location #3 Are the slabs level
Finishing the slab with the whirly bird and beginning to remove the formwork.
→Underground Plumbing
byKevin 07/30/10
We're almost out of the ground on D+J. And on a hillside project like this once the foundations are in and the slabs are poured the rest is all downhill.
In this picture the plumbing is in and the rebar and anchor bolts are in position (bottom of pic with 2x4 bracing). The retaining wall in the foreground is the elevation change between the living room and dining room. The retaining wall in the background is the back of the house behind the kitchen cabinets.
→Eastsider LA Interview
byKevin 06/17/10
Follow the link below to read the interview on The Eastsider LA blog:
www.theeastsiderla.com/2010/06/will-dick-and-jane-feel-at-home-in-echo-park/

