CONSTRUCTION BLOG: DICK + JANE


Facade Framing

by
Kevin 09/21/10


The final shape of the buildings is coming together.

image


Framing Nearing Completion

by
Kevin 09/15/10


Framing is about 90% complete as of today. The mechanical, electrical, and plumbing are also roughed in. We hope to start on the insulation sometime next week.

image


Framing Has Begun

by
Kevin 08/09/10


Now that the slabs are in the spaces are starting to take shape. We hope to have the majority of the framing complete by the end of the month.
image
That poor little baby banana plant in the foreground is about to get transplanted to our office garden.


Slabs Poured

by
Kevin 08/04/10


We are finally out of the ground! The slabs were poured today and the project finally looks like something.

Here they are placing the last couple of yards of concrete. The pour took 45 yards for both houses which is 5 trucks of concrete. Warren (the guy holding the hose) is the pump operator. We've been working with him for about 8 years on all our hillside projects. He pumps the concrete from the truck to the slab and then the concrete sub finishes it. The slab shown has two layers of massive #8 rebar (the steel that works in tension with the compressive strength of the concrete) which is 1" thick.
image

The obvious things to look out for are: #1: Is all your structural hardware in the right location #2 Is all your rough plumbing in the right location #3 Are the slabs level
image

Finishing the slab with the whirly bird and beginning to remove the formwork.
image


Underground Plumbing

by
Kevin 07/30/10


We're almost out of the ground on D+J. And on a hillside project like this once the foundations are in and the slabs are poured the rest is all downhill.
In this picture the plumbing is in and the rebar and anchor bolts are in position (bottom of pic with 2x4 bracing). The retaining wall in the foreground is the elevation change between the living room and dining room. The retaining wall in the background is the back of the house behind the kitchen cabinets.

image


Eastsider LA Interview

by
Kevin 06/17/10


Follow the link below to read the interview on The Eastsider LA blog:

www.theeastsiderla.com/2010/06/will-dick-and-jane-feel-at-home-in-echo-park/


<< Previous Page

    

Next Page >>



Buildings and their Construction Blogs

HEYDAY HOMES: Peak Place

Six LEED Rated Homes in Glassell Park

Slab City 05/14/13

Three slabs down, three to go.



image

Site Grading and Foundations 05/01/13

The foundation footings are currently being formed and we hope to pour them in the next couple days. Unlike most…

HEYDAY HOMES: Peak Place

HEYDAY HOMES: Rennie

Three LEED Rated homes in Venice

Retaining Walls 05/02/13

The retaining walls for the sunken courtyards are being formed. Since the walls surround the courtyard and extend to the…

$ in the Ground 04/04/13

We poured the footings for one of the houses today. It took 30 yards of concrete, which happens to cost…

HEYDAY HOMES: Rennie

HEYDAY HOMES: Buzz Court

Six LEED Rated Homes in Silver Lake

COMPLETE 12/06/12


HEYDAY HOMES: Buzz Court

HEYDAY HOMES: Ellenwood

19 LEED Rated Townhomes in Eagle Rock.

SOLD 08/17/11


HEYDAY HOMES: Ellenwood

DICK + JANE

Two Homes in Echo Park.

COMPLETE 05/01/11


DICK + JANE

ROCK ROW

15 LEED Platinum + Gold Townhomes in Eagle Rock.

COMPLETE 02/01/10


ROCK ROW

B(L)OX

A renovated duplex in Echo Park.

COMPLETE 09/02/07


B(L)OX

JACK + JILL

Two homes in Lincoln Heights.

COMPLETE 02/10/06


JACK + JILL

4xFOURPLEX

An apartment building in Echo Park.

COMPLETE 10/27/04


4xFOURPLEX

A+D Museum Installation

Installation at Architecture + Design Museum. Summer 2011

See the video 08/22/11


A+D Museum Installation
Read full Heyday blog