COMPLETE
by Kevin 10/27/04category: 4xFOURPLEX
Party Time! The project is finally complete, Temporary Certificate of Occupancy has been received, and the celebration has begun! Tacos on the roof deck, spinning by KJ, plenty of drinks, a light rain, and 200 of our closest friends made for one hell of a night.
The units are renting for about $200/month more than the pro-forma so we have money to spend on the next piece of land. All the tenants are hipster young professionals or students that were looking for a nicer design without having to pay for a swanky neighborhood.
Final Inspection
by Kevin 10/22/04category: 4xFOURPLEX
Approved by the City so we can start renting this sucker and actually make some money.
tags:
bureaucracy
tags:
Insulation
by Kevin 10/11/04category: 4xFOURPLEX
With all the systems finally installed insulation is in. Great to see the individual spaces of the units for the first time.

The unit 4 living room is pictured.
tags:
insulation,
construction
The unit 4 living room is pictured.
tags:
L.A. Forum Lecture
by Kevin 07/08/04category: 4xFOURPLEX
Tonight we're lecturing about our project as part of the L.A. Forum's 'On The Map' lecture series. The weekly series visits projects every week to hear lectures by the designers. We're sandwiched between Neil Denari and Wes Jones so we hope not to disappoint. Oh, and the building is only about 90% complete so we've been killing ourselves trying to get ready for this.
tags:
education
tags:
Driver’s Ed.
by Kevin 02/20/04category: 4xFOURPLEX
Hardy learning to drive a Grad-All and placing a 20 ft. steel beam simultaneously

While Kevin and their dad, Doug Wronske, place the beam.

tags:
education
While Kevin and their dad, Doug Wronske, place the beam.